Santa Fe Pedestrian Improvements

Job No.:

2015-008

Services: 

Concrete, Earthwork, Asphalt

Owner: 

City of El Paso – Capital Improvements Department

Status:

Started January 5, 2015 – Completed

Scope of Work

Project consisted of installation/replacement of sidewalk and landscaping along Santa Fe St. between Main Dr. and San Antonio Ave. Pedestrian facilities to be installed with this project consist of widening of the sidewalk at the northeast corner of the intersection with San Antonio, new curb and gutter, new ADA accessible curb ramps, new stamped/colored crosswalks, introduction of landscaping elements such as 3” caliper trees with grates, new irrigation system, and new street lights typical to the ones located in the downtown area.

Original Contract Time: 90 calendar days (3 months)

Completion Time: 3 months (on time)

Major Subcontractors/Suppliers:

Prime Irrigation & Landscape, Code Electric, Pavement Markings Inc., Paso del Norte Materials.

MORE PROJECTS

  • River Bend Dr Pedestrian and Bicycle Enhancements
  • Pedestrian Pathway Improvements Phase 1.2B
  • Pedestrian Pathway Improvements Phase 1.2A
  • Pedestrian Pathway Improvements Phase 2.1
  • Scenic Drive
  • Roundabouts
  • Pedestrian Crossings
  • City Site Work
  • Independence Dr Pedestrian and Bicycle Enhancements
  • El Paso Int. Airport Runway
  • Loop 375 Widening

Pedestrian Crossings

Job No.:

2014-246

Services: 

Concrete, Earthwork

Owner: 

City of El Paso – Capital Improvements Department

Status:

Started September 30, 2014 – Completed

Scope of Work

Project consisted of a pedestrian platform extending from the ballpark site over the Bataan Railway to the South and a smaller pedestrian bridge extending from the ballpark site over the Bataan Railway to the South. The platform and bridge both had deep foundations on the South side of the Bataan Railway.  Project scope for the platform included the following: 70’ piers, structural steel members and a metal deck with poured concrete on the Eastern 1/3rd of the platform and structural steel members with removable precast slabs on the Western 2/3rds of the platform. There are steps from Santa Fe Street up to the platform, a set of pilasters with fencing and gates in between, and a trellis. Project also included a lit signage element hanging from the trellis with a minimal amount of electrical outlets and lighting surrounding the platform. On the South side of the platform a steel fence sits on top of the brick wall. The North side of the platform tied in with the ballpark hardscape.

Original Contract Time: 200 calendar days (7 months)

Completion Time: 7 months (on time)

Major Subcontractors/Suppliers:

Vertex Contractors, Paso Del Norte Materials.

MORE PROJECTS

  • Pedestrian Pathway Improvements Phase 2.1
  • Independence Dr Pedestrian and Bicycle Enhancements
  • City Site Work
  • River Bend Dr Pedestrian and Bicycle Enhancements
  • Pedestrian Pathway Improvements Phase 1.2A
  • Scenic Drive
  • Roundabouts
  • Santa Fe Pedestrian Improvements
  • Pedestrian Pathway Improvements Phase 1.2B
  • El Paso Int. Airport Runway
  • Loop 375 Widening

Pedestrian Pathway Improvements Phase 1.2A

Job No.:

2013-188

Services: 

Concrete, Earthwork

Owner: 

City of El Paso – Capital Improvements Department

Status:

Started January 2014 – Completed

Scope of Work:

Project consisted of a new pedestrian pathway at the downtown chamber of commerce parking lot on the Santa Fe street side. Project consisted of removing the existing asphalt pavement and landscaping, new decorative sidewalks, amphitheatre type stairs, new landscape & irrigation, new lighting, electrical room. Underground utilities & foundation of art piece.

Original Contract Time: 15 months.

Completion Time: 14 months (ahead of time)

Major Subcontractors/Suppliers:

Code Electric, Prime Irrigation & Landscape, Steel Specialties, EP Bestway Construction, Centeno Construction, Paso Del Norte Materials.

SIMILAR PROJECTS

  • Loop 375 Widening
  • Independence Dr Pedestrian and Bicycle Enhancements
  • Roundabouts
  • City Site Work
  • El Paso Int. Airport Runway
  • Pedestrian Pathway Improvements Phase 1.2B
  • Santa Fe Pedestrian Improvements
  • Pedestrian Crossings
  • Pedestrian Pathway Improvements Phase 2.1
  • Scenic Drive
  • River Bend Dr Pedestrian and Bicycle Enhancements

Independence Dr Pedestrian and Bicycle Enhancements

Job No.:

2015-828

Services: 

Concrete, Asphalt, Earthwork

Owner: 

City of El Paso – Capital Improvements Department

Status:

Started February 8, 2016

Scope of Work:

The project supports the development of a pedestrian and bicycle corridor along Independence Dr. between Yarbrough Dr. and Whittier Dr. The project consists of a 14 ft. pedestrian and bicycle path with shade trees, vegetation and other amenities.  The corridor will provide connectivity to several existing neighborhoods, J.P. Shawyer Park, and the existing Yarbrough Dr. bike lane. The total length of the pedestrian and bicycle corridor project is 4,765 feet and runs parallel to Independence Dr.

Original Contract Time:

161 calendar days (5 ½ months)    Anticipated Completion Time: 4 months

Major Subcontractors/Suppliers:

Accent Landscape Contractors, Code Electric, Bowen Industrial Contractors, Pavement Markings Inc., Paso Del Norte Materials, CEMEX.

SIMILAR PROJECTS

  • El Paso Int. Airport Runway
  • Pedestrian Pathway Improvements Phase 2.1
  • Roundabouts
  • Pedestrian Pathway Improvements Phase 1.2B
  • Pedestrian Crossings
  • Scenic Drive
  • Pedestrian Pathway Improvements Phase 1.2A
  • Santa Fe Pedestrian Improvements
  • River Bend Dr Pedestrian and Bicycle Enhancements
  • Loop 375 Widening
  • City Site Work

River Bend Dr Pedestrian and Bicycle Enhancements

Job No:

2015-780

Services:

Concrete, Asphalt, Earthwork, Utilities

Owner: 

City of El Paso – Capital Improvements Department

Status:

Started February 12, 2016

Scope of Work:

The project supports the development of a pedestrian and bicycle corridor along River Bend Dr. between Frontera Rd. and Turnstone Dr. The project consists of a 12 ft. pedestrian and bicycle path with shade trees, vegetation and other amenities.  The corridor will provide connectivity to several existing neighborhoods, Braden Aboud Park and Zach White Elementary School. The total length of the pedestrian and bicycle corridor project is 5,633 feet and runs parallel to River Bend Dr.

Original Contract Time:

193 calendar days (6 ½ months)    Anticipated Completion Time: 5 months

Major Subcontractors/Suppliers:

Accent Landscape Contractors, Code Electric, Bowen Industrial Contractors, Pavement Markings Inc., Vertex Contractors, Paso Del Norte Materials, CEMEX.

SIMILAR PROJECTS

  • City Site Work
  • Santa Fe Pedestrian Improvements
  • Scenic Drive
  • Pedestrian Pathway Improvements Phase 1.2A
  • Pedestrian Crossings
  • Pedestrian Pathway Improvements Phase 2.1
  • Pedestrian Pathway Improvements Phase 1.2B
  • Loop 375 Widening
  • Roundabouts
  • Independence Dr Pedestrian and Bicycle Enhancements
  • El Paso Int. Airport Runway

Loop 375 Widening

CN:

2552-03-054

Services:

Concrete, Asphalt, Earthwork, Utilities

Owner:

TXDOT

Status:

Started March 28, 2016

Scope of Work:

Project consists of the construction of an additional travel lane in both directions on Loop 375, an auxiliary lane, high mast illumination, signing, pavement markings, delineators, metal beam guard fence adjustment and frontage road sidewalks.

Original Contract Time:

452 working days (20 months)    Anticipated Completion Time: 14 months

Major Subcontractors/Suppliers:

Tri-State Electric, Pavement Markings Inc., Traffic Control Specialist, Vertex Contractors, EGL Construction, Texas Far West, A-Brothers, Hardy Hole Drilling, South Texas Painting, Paso Del Norte Materials, CEMEX, Castillo Prestress.

SIMILAR PROJECTS

  • Pedestrian Pathway Improvements Phase 2.1
  • Scenic Drive
  • Santa Fe Pedestrian Improvements
  • Pedestrian Pathway Improvements Phase 1.2B
  • River Bend Dr Pedestrian and Bicycle Enhancements
  • Pedestrian Pathway Improvements Phase 1.2A
  • El Paso Int. Airport Runway
  • Roundabouts
  • City Site Work
  • Independence Dr Pedestrian and Bicycle Enhancements
  • Pedestrian Crossings