CN:
2552-03-054
Services:
Concrete, Asphalt, Earthwork, Utilities
Owner:
TXDOT
Status:
Started March 28, 2016
Scope of Work:
Project consists of the construction of an additional travel lane in both directions on Loop 375, an auxiliary lane, high mast illumination, signing, pavement markings, delineators, metal beam guard fence adjustment and frontage road sidewalks.
Original Contract Time:
452 working days (20 months) Anticipated Completion Time: 14 months
Major Subcontractors/Suppliers:
Tri-State Electric, Pavement Markings Inc., Traffic Control Specialist, Vertex Contractors, EGL Construction, Texas Far West, A-Brothers, Hardy Hole Drilling, South Texas Painting, Paso Del Norte Materials, CEMEX, Castillo Prestress.