CN:

2552-03-054

Services:

Concrete, Asphalt, Earthwork, Utilities

Owner:

TXDOT

Status:

Started March 28, 2016

Scope of Work:

Project consists of the construction of an additional travel lane in both directions on Loop 375, an auxiliary lane, high mast illumination, signing, pavement markings, delineators, metal beam guard fence adjustment and frontage road sidewalks.

Original Contract Time:

452 working days (20 months)    Anticipated Completion Time: 14 months

Major Subcontractors/Suppliers:

Tri-State Electric, Pavement Markings Inc., Traffic Control Specialist, Vertex Contractors, EGL Construction, Texas Far West, A-Brothers, Hardy Hole Drilling, South Texas Painting, Paso Del Norte Materials, CEMEX, Castillo Prestress.

SIMILAR PROJECTS

  • City Site Work
  • El Paso Int. Airport Runway
  • Pedestrian Pathway Improvements Phase 1.2B
  • Scenic Drive
  • Independence Dr Pedestrian and Bicycle Enhancements
  • River Bend Dr Pedestrian and Bicycle Enhancements
  • Pedestrian Pathway Improvements Phase 1.2A
  • Santa Fe Pedestrian Improvements
  • Pedestrian Crossings
  • Pedestrian Pathway Improvements Phase 2.1
  • Roundabouts